What to do before starting

The actual installation is only part of the schedule, also allow time for clearing the flat before work begins and for a thorough clean after handover, which is often underestimated in estimates.

Realistic schedule: complete flat renovation

WeekWhat is happening
1Demolition of partitions, dismantling of the core, removal of rubble.
2-3New installations: water, drainage, electricity, and risers if required
4New partitions, bathroom core, rough plastering and screeds
5-6Wall and floor tiling, adhesive curing, plasterboard installation.
7Installation of kitchens, sanitary ware, doors and floor coverings
8Painting, minor finishing works, cleaning, handover

This is the schedule for a flat around 2+kk to 3+kk without major complications. A larger flat, layout changes involving structural engineering or waiting for custom-made materials (kitchen, doors) extends the total time to 10-12 weeks. A smaller cosmetic renovation can be completed in 2-3 weeks, as demolition and drying of wet processes are not required.

What most often slows down the schedule

The schedule is not created to be followed down to the day; it exists to clarify what caused delays and why.

Shorter schedule for partial refurbishment

Not every renovation requires eight weeks. If you are only renovating the bathroom and kitchen without changing the layout, allow for 4-6 weeks, most of the time is taken up by demolition and installing the new bathroom core, with the rest running concurrently. A purely cosmetic renovation (flooring, painting, doors) involving no demolition or wet trades can often be completed in 2-3 weeks, as the longest phase: the curing of plaster and screeds, is eliminated.

How to monitor the schedule throughout the process

Arrange a regular brief report with the company: a weekly photo of progress and a sentence confirming whether the schedule is being kept are sufficient. This is not a lack of trust; it is standard practice that saves both parties from unpleasant surprises on the planned handover date. If the company agrees to a regular report without hesitation, this is in itself a good sign.

A company that can provide a realistic schedule: not just "within two months" - and stick to it is one of the things we monitor with vetted firms.

Do you want three such offers side by side, including an estimate of the implementation duration?

Submit your flat

Before you begin, read this too How to spot a rogue trader and indicative prices depending on scope.

Related articles